Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
ALE’s bridge removal in Serbia improving river navigation
Photo Credit To ALE

ALE’s bridge removal in Serbia improving river navigation

ALE’s bridge removal in Serbia improving river navigation

ALE performed the removal of a bridge over the Danube river in Novi Sad, Serbia as the height of the old bridge limited river traffic during high water levels and its curve radius had reduced the fairway width. Its removal would provide safer and more efficient river navigation for the city.

A solution was needed to perform the removal operation while overcoming the river’s strong current. To achieve this, ALE mobilised several of its transportation, jacking and ballasting technologies to complete the project as a single point of contact.

The bridge was to be removed in sections, with four spans weighing 200t and measuring 75m long, while the fifth weighed 360t and measured 200m long. They would be jacked-up before being floated over to a jetty, where they were loaded-in.

Equipment was delivered to Serbia and assembled and installed at a local assembly area, 20km from the bridge. ALE’s Mega Jack 800 was installed with modular spreader beams on a ballastable modular pontoon. With a capacity of 800t per tower, Mega Jack 800 allowed the load to be lifted and distributed appropriately while making best use of the pontoon’s limited space and capacity.

This was especially important during the pontoon’s navigation to the jetty from its initial position between the bridge piers.

ALE connected 20t capacity winches to each corner of the pontoon and secured them to the piers throughout the jacking operations. Three tug boats also pushed and guided the pontoon at all times. At the jetty, the winches were used to adjust the pontoon into position.

ALE's bridge removal in Serbia is improving river navigation

To remove the bridge spans, the Mega Jack 800 was used to jack-up each span, which was then transported to the jetty on the pontoon. The pontoon was de-ballasted to perform the jack-down operation over the jetty and the Mega Jack 800 unloaded the spans onto a skidding system.

The removal of the bridge in Serbia will eliminate congestion on the European Rhine-Danube Corridor, enabling improved transport safety and more efficient river navigation on the city’s waterway. This will help the Danube region with its aim to increase cargo transport on the river by 20%.

ALE previously completed the installation of a new replacement bridge over the Danube river.

Post source : ALE

About The Author

Anthony brings a wealth of global experience to his role as Managing Editor of Highways.Today. With an extensive career spanning several decades in the construction industry, Anthony has worked on diverse projects across continents, gaining valuable insights and expertise in highway construction, infrastructure development, and innovative engineering solutions. His international experience equips him with a unique perspective on the challenges and opportunities within the highways industry.

Related posts