Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Header Banner – Finance
Doka experience leads the way in Aurach Bridge reconstruction
Photo Credit To Doka GmbH

Doka experience leads the way in Aurach Bridge reconstruction

Doka experience leads the way in Aurach Bridge reconstruction

With a height of 50 metres, the Aurach Bridge is the highest bridge on the Austrian A1 motorway. It is frequented by around 50,000 vehicles a day at peak times. Now after 60 years in service, the steel composite bridge needs to be completely renewed. As an experienced partner in balanced cantilever construction, the formwork specialist Doka is involved in the new construction of this important traffic link.

An efficient way for traffic to cross the Aurach valley must continue to be available despite the upcoming construction activities. Therefore, a new supporting structure first will be built parallel to the existing bridge, onto which traffic will be temporarily diverted from the end of 2023, while the new bridge designed for significantly higher loads will be built.

The executing consortium HABAU/PORR is relying on Doka’s know-how to ensure that the new Aurach bridge can act as a functional and reliable transport link across the Aurach valley for at least the next hundred years. The Doka technicians’ many years of experience and the customised solutions in balanced cantilever construction are indispensable in the implementation of this major project.

For each of the bridge’s five piers, 30 bored piles with a depth of up to more than 30 metres were needed. Austria’s largest rotary drilling rig with an operating weight of 180 tonnes was used in 2022 to prepare the ground. Then, in autumn 2022, concrete was poured for the five foundations on which the piers, each weighing several tonnes, were moved into place and erected. Framed formwork Framax Xlife and Doka’s MF240 climbing formwork were used to construct these piers, which are up to 40 metres high.

Doka experience leads the way in Aurach Bridge reconstruction

Concreting using the balanced cantilever method

After completion of the piers, the so-called hammerheads that serve as the respective starting points for the balanced cantilever construction method were concreted on top of them. The Doka cantilever forming travellers are now being used for precisely this procedure, which combines planning and cost reliability with an optimum construction sequence. The perfect coordination between the falsework and the formwork, the high safety standard and the optimised ergonomics ensured that construction progressed swiftly and safely. In this way the subsequent construction sections can be added in parallel to each of the freely projecting ends of the hammerheads.

“The challenge here is the short length of the hammerheads that make it impossible to fit the two cantilever forming travellers one after the other or side by side,” explains Markus Stastny, Technical Manager at Doka Austria. His team came up with the so-called “fork solution” as an answer. “On the one hand, this allows the traveller to be placed inside each other in a space-saving way and on the other hand, as little conversion work as possible is required during the balanced cantilever construction planned with DokaCAD for Revit”, says Stastny. Beginning in March 2023, the superstructure will be built symmetrically in 5-metre sections, starting from the hammerheads.

Doka experience leads the way in Aurach Bridge reconstruction

Rapid construction progress thanks to concrete monitoring system

To accommodate the tight construction schedule, Doka’s Concremote concrete monitoring system is in use as part of the balanced cantilever construction. The sensors provide reliable data on concrete strength, enabling safe post-tensioning of the bridge tension cables.

Due to the high demands of the construction site, a new reporting function was also implemented for the HABAU/PORR consortium, enabling detailed recording of the measured values in all concreting sections. This included significant time savings in documentation.

Doka experience leads the way in Aurach Bridge reconstruction

That was just the beginning

Once the first superstructure is completed and the carriageway is asphalted, at the end of 2023 all traffic will be diverted onto these sections in two lanes, so that the actual construction of the new Aurach Bridge can begin.

First, the two old supporting structures including the carriageway and the associated piers will be removed. Subsequently, separate piers will be erected for each directional carriageway and the supporting structure including the carriageway in the direction of Vienna will be completed.

Then the actual masterpiece, which requires millimetre work, will be completed: The supporting structure in the direction of Salzburg, with a weight of approx. 15,000 tonnes, will be moved from the bridge to the new piers by means of a transverse shifting procedure. After this, the temporary piers of the bridge will be removed.

Doka experience leads the way in Aurach Bridge reconstruction

Good to know

The new Aurach bridge will ensure a future-proof infrastructure according to the latest technology and standards. Almost all the material removed from the old and temporary substructures will be recycled: The concrete will be crushed, processed and reused as construction material.

In addition, around 4,000 new trees will be planted to renature the construction site.

Doka experience leads the way in Aurach Bridge reconstruction

Project Specs

  • Project: New construction of the Aurach Bridge
  • Location: Regau, Austria
  • Type of structure: Prestressed concrete bridge
  • Construction company: ARGE HABAU/PORR
  • Traffic opening: End of 2025
  • Overall completion: Beginning of 2026
  • Systems in use: Doka cantilever forming travellers, Framax Xlife panel formwork, Climbing formwork MF240, Shaft platforms, Staxo stair tower, Large-area formwork Top50
    Services in use: Concremote concrete monitoring (8 sensors)

Post source : Doka GmbH

About The Author

Anthony brings a wealth of global experience to his role as Managing Editor of Highways.Today. With an extensive career spanning several decades in the construction industry, Anthony has worked on diverse projects across continents, gaining valuable insights and expertise in highway construction, infrastructure development, and innovative engineering solutions. His international experience equips him with a unique perspective on the challenges and opportunities within the highways industry.

Related posts