Rebuilding Route E45 in Denmark with Sustainable Cold Recycling
A 6.5 km section of the European Route E 45 highway not far from Denmarkβs world famous Legoland theme park had to be completely rehabilitated in both directions. The highly-respected contractor, SR-Gruppen A/S, which already has considerable experience in the use of the sustainable cold recycling method, was commissioned by the Colas Group to carry out the removal of the existing asphalt and the paving of the new base layer.
The tender for the job foresaw the paving of a 20 cm base layer with a cold mix produced by complete recycling of the material from the existing asphalt pavement.
The construction work was carried out by SR-Gruppen A/S with a mobile cold mixing plant KMA 240i from Wirtgen.

Cold recycling of road surface material is the most sustainable construction method available for structural rehabilitation. Bituminous cold mix, as used here for the paving of the new base layer, is produced by the addition of foamed bitumen to the crushed, milled material and has become established around the globe as an ideal material for paving roads of all load classes.
As the deadline for the completion of the project was extremely tight, it was essential to ensure that everything and everybody worked hand-in-hand. βWe produced up toΒ 300Β tΒ of cold mix per hour with theΒ KMA 240iβ, reportsΒ Morten Wold,Β Divisional Manager atΒ SR-Gruppen A/S.
The asphalt pavement of theΒ E45Β motorway was milled off to a width of betweenΒ 3.15Β mΒ andΒ 5.9Β mΒ and a depth ofΒ 28Β cmΒ by Wirtgen large milling machinesΒ W 210iΒ andΒ W 250i. The milled asphalt was transported to a mixing site set up close to the construction site for processing by theΒ KMA 240i. The mobile cold mixing plant enabled the contractor to stay close to the asphalt removal and paving location, which consequently minimised material transport requirements and significantly reduced the overall COβ emissions of the construction project.

A suitability test was carried out on the reclaimed asphalt pavement (RAP) before the start of the construction phase. An ideally formulated mix was achieved by the addition ofΒ 2.2%Β of foamed bitumen,Β 6%Β of lime andΒ 0.8%Β of cement.
SR-Gruppen A/S achieved a mix particle size ofΒ 0-32Β mmΒ by pre-treatment in an impact crusher and then used theΒ KMA 240iΒ to produce up toΒ 300Β tΒ of cold mix per hour.
The top quality mix was loaded into the high-capacity receiving hopper of theΒ KMA 240iΒ by a wheel loader and fed to the twin-shaft continuous mixer. The two feed augers of the double-trough system with precision weighing took care of the separate addition of lime and cement binding agents. Wirtgen extended the capabilities of theΒ KMA 240iΒ on the spot by installing an additional feed auger. The continuous weighing system ensured precise dosing of the required additives.

The cold mix was loaded directly intoΒ 36.5Β tΒ dump semi-trailers by the plantβs high-capacity discharge conveyor and immediately transported back to the construction site. Graders andΒ Hamm rollersΒ prepared and consolidated the frost protection layer beneath the milled off asphalt pavement as a stable roadway for the pavers and trucks following on behind.
AΒ MT 3000-3i OffsetΒ mobile feeder from VΓΆgele served as a material feeder to ensure a smooth and seamless material flow on the construction site. The high-capacity receiving hopper of theΒ MT 3000-3i OffsetΒ ensures an uninterrupted supply of large quantities of cold mix. As no complete road closures were permitted during the project, the material transport logistics involved were extremely challenging. TheΒ MT 3000-3i OffsetΒ delivered the decisive leeway required for the complete rehabilitation of two lanes of the motorway in a single pass without the need for closing them to traffic.

A VΓΆgeleΒ SUPER 1900-3iΒ paver laid down the material true to grade and slope to create aΒ 20Β cmΒ base layer of cold mix as the new basis of the busy highway. Particular care was taken during the subsequent compaction process. A HammΒ HD 120iΒ tandem roller with an operating weight of overΒ 12Β tΒ provided the necessary compaction. A HammΒ GRW 280iΒ pneumatic-tyre roller then took over the task of thin cape seal surfacing.
After only two days, Colas was able to lay down a binder course and a surface layer with a thickness ofΒ 8Β cm. Here, Colas chose a polymer-modified asphalt that caters for the special demands on the particularly busy HGV lane. A perfect complement to the base layer of cold recycling mix with foamed bitumen. A VΓΆgeleΒ SUPER 1900-3iΒ and aΒ MT 3000-3i OffsetΒ worked hand-in-hand here, too.

Wirtgen Group machines deployed on the project
- WirtgenΒ KMA 240i
- WirtgenΒ W 210i
- WirtgenΒ W 250i
- WirtgenΒ W 100 CFi
- 2x VΓΆgeleΒ SUPER 1900-3i
- 2x VΓΆgeleΒ MT 3000-3i Offset
- HammΒ HD 120i
- HammΒ GRW 280i
- HammΒ H 7i
Project details
- Length of section: 6,500Β m
- Width of the section: all lanes, 20.45Β m
- Reduction of material transport requirements: > 70%
- Cold mix qty. paved: 51,000Β t
- Reduction of COβ emissions: > 50%
- Project completion time: 50% faster (approx.)
















