Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders
Photo Credit To Liebherr

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders

After roughly ten months of construction, Liebherr has commissioned a new assembly hall especially for the manufacture of battery-electric wheel loaders at their plant in Bischofshofen. The group’s first electric wheel loader, the L 507 E, has been rolling off the assembly line here since March 2024.

In total, Liebherr has invested over €2.2 million in the new manufacturing facilities. The nearly 1000 m² production area is designed for a maximum yearly output of up to 500 battery-electric wheel loaders.

In order to uphold the most stringent safety standards, the new production area is located in a separate hall, away from the conventional wheel loader assembly. “This separate space is something we opted for because we wanted to fully adapt the new assembly hall to meet the work-safety measures required by the new high-voltage battery system.

“All employees involved in constructing the L 507 E receive specialised training, which means we are particularly well prepared to meet the demands of electrical technology,” explains Peter Schachinger, Director of Production and Operations at Liebherr-Werk Bischofshofen.

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders
Peter Schachinger (2nd from left, Director of Production and Operations) and Jonas Schwob (3rd from left, Project Manager for the Production of Electric Wheel Loaders) celebrate the commissioning of the new assembly hall at Liebherr-Werk Bischofshofen together with members of the project team.

Designed using virtual reality: a modern wheel loader assembly line that uses space intelligently

The new wheel loader assembly line is located in one of the plant’s former workshop halls, which Liebherr has gutted and restored for the production of the L 507 E. The building is now characterised by its expansive windows, which create a friendly working environment. Liebherr has also invested in new break rooms for its employees.

“We’ve also brought the building up to the latest energy standards, with concrete core activation, a district heating connection and heat pumps. We’re increasingly generating the electricity required for the hall ourselves, as we now operate several solar panels at our plant – which cover over 3400 square metres in total,” Schachinger explains.

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders
Liebherr wheel loader L 507 E: Full power, long run times and efficient charging thanks to the high-voltage battery system.

The wheel loader experts designed the interior of the assembly hall almost entirely digitally using virtual reality applications. “This allowed us to test various layouts and therefore perfectly coordinate the pre-assembly stations and the main assembly line. We were therefore able to efficiently use the available space and create short transport paths,” says Jonas Schwob, Project Manager for the Production of Electric Wheel Loaders. A digital display at the centre of the assembly hall gives an overview of the current key production figures in real time.

Liebherr has given special consideration to ergonomics at the individual work stations: Special lifting devices and transport systems as well as wireless bolting tools make it easier for workers to assemble the new L 507 E wheel loader.

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders
The wheel loader experts in Bischofshofen designed the new assembly line almost entirely digitally using virtual reality applications.

Liebherr L 507 E wheel loaders: maximum performance with a high-voltage battery system

The new L 507 E has been available from Liebherr sales partners in several European countries since late 2023. It is based on the conventionally driven L 507 Stereo wheel loader and combines the tried-and-tested advantages of a stereoloader with a battery-electric drive developed by Liebherr.

This drive relies on a high-voltage battery system, specially designed by Liebherr for wheel loader operations, ensuring powerful performance and efficient charging.

While the L 507 E’s performance is identical to conventionally driven Liebherr wheel loaders of the same size class, it emits no local CO2, and noise emissions are minimal. This makes the new wheel loader particularly suitable for any operation where you have to consider noise or exhaust fumes, such as in inner-city areas or in halls.

Depending on the operating conditions, the L 507 E has a run time of up to eight hours. Liebherr’s modular battery design also makes it possible to install a second lithium-ion battery ex works at the customer’s request, which further extends the run time. A full battery charge can take between ninety minutes and three hours, depending on the on-board charging technology and power rating.

Liebherr commissions new Manufacturing Assembly Hall for Electric Wheel Loaders
Just before production start-up: The new assembly hall for Liebherr’s L 507 E battery-electric wheel loader.

Post source : Liebherr

About The Author

Anthony brings a wealth of global experience to his role as Managing Editor of Highways.Today. With an extensive career spanning several decades in the construction industry, Anthony has worked on diverse projects across continents, gaining valuable insights and expertise in highway construction, infrastructure development, and innovative engineering solutions. His international experience equips him with a unique perspective on the challenges and opportunities within the highways industry.