Highways England upgrades A14 – bridge foundations, Roman cows and a floating pontoon
Photo Credit To Highways England

Highways England upgrades A14 – bridge foundations, Roman cows and a floating pontoon

Highways England upgrades A14 – bridge foundations, Roman cows and a floating pontoon

Highways England project manager gives a sneak peek into the progress on the UK’s biggest road upgrade under construction.

Three months in to main construction on the A14’s £1.5bn upgrade in Cambridgeshire, Highways England’s project manager is giving a sneak peek into progress made so far – including technical innovations and archaeological finds.

Much has been achieved since main construction on the A14 Cambridge to Huntingdon improvement scheme, Highways England’s biggest scheme currently in construction, started at the end of November last year.

progress on the A14 Cambridge to Huntingdon scheme - River Great Ouse crossing taking shape
progress on the A14 Cambridge to Huntingdon scheme – River Great Ouse crossing taking shape

Chris Griffin, A14 project manager at Highways England, talks through progress so far, “As yellow diggers have become a familiar sight along the A14 corridor in Cambridgeshire, drivers will have noticed the changes along the existing A14. But there is plenty happening that they might not have noticed.”

Traffic management

Chris explains, “The narrow lanes, temporary speed limits, cones and barriers we’ve installed allow workers to build accesses for construction traffic and carry out vegetation clearance ahead of the bird nesting season while keeping disruption on the road to a minimum and keeping road users safe.”

All the trees that have been cut are being used as biomass for energy production locally and more trees will be replanted when the project nears completion.

Chris continues, “We are committed to keeping the main roads at full capacity during the day, so we only use overnight lane or carriageway closures if it is absolutely necessary, like for instance if we need to install signs or barriers, carry out pavement surveys or strengthen the carriageway where heavy machinery will need to cross on a regular basis. We’ve also installed CCTV cameras along the A14 so we can actively manage disruption to road users from a dedicated control room within the scheme’s main compound. This helps us to stay aware at all times of conditions on the road and to take measures quickly if things don’t go to plan.”

the A14 project CCTV control room
the A14 project CCTV control room

But the most interesting activities to date are probably the ones that can’t be seen from the road.

Construction of the River Great Ouse Viaduct

Chris explains, “A significant part of the scheme is a new bypass, including a viaduct over the River Great Ouse, which will run south of Huntingdon. This bypass is a brand new road so is being built away from the existing A14, with no disruption to road users other than when plant occasionally cross local roads while travelling along the new construction haul roads. Work on this section of the project is progressing well and to schedule. Building the 750-metre long River Great Ouse viaduct, which will carry the new A14 across the flood plain and river, is a complex task. The first step has been to install a pontoon which has a 52 tonne capacity, allowing fully laden dump trucks and plant access across the river. This pontoon is allowing us to install a temporary bridge so we can start building the viaduct itself.”

the pontoon to help build the Building the River Great Ouse viaduct
the pontoon to help build the Building the River Great Ouse viaduct

Construction of the foundations and columns for the viaduct is also under way, with plans for later this year to start installing the steelwork that supports the bridge deck and start casting the 800 concrete panels needed for the viaduct.

Chris adds, “We have also been building foundations for several of the new bridges. People may have noticed our construction teams installing giant steel cages along the A1 recently. Once these are in place, concrete will be poured around them to form the bridge foundations and we’ll be able to start building the bridges themselves.”

Archaeology

The Archaeological team has also made great progress since starting excavations last autumn following extensive surveys and trial trenching. The team identified important archaeological remains dating from the prehistoric period through to the Romano-British and medieval periods.

Chris says, “The trial trenching identified some 350 hectares of land that our archaeologists would need to look at. Most of the remains show evidence of settlements or industrial activity, including a well-preserved series of Romano-British pottery kilns, some carving tools and even the remains of a cow.”

one of the trial trenches on the A14 scheme
one of the trial trenches on the A14 scheme

Excavations will be taking place across the scheme throughout 2017 and the team is planning on presenting findings to the local community once the archaeological work is finished.

Chris says, “I am pleased with progress so far on the scheme, we have a challenging timetable to deliver the scheme and open the new A14 to traffic by the end of 2020, so it is good to see the speed at which work is progressing as well as the innovative solutions we are using to tackle challenges.”

Work achieved to date:

  • 3 main compounds have been built at Brampton (just off the A1), Ermine Street (A1198) and Swavesey (near Cambridge Services). A smaller compound has been established within the Girton Interchange and a second compound at Brampton is taking shape
  • 3.3km of temporary safety barriers installed along the A14, A428 (near Girton) and A1
  • 9 earthworks teams have started stripping topsoil along the offline section of the project
  • 128 piles have been installed, using nearly 8,000m3 of concrete to create foundations for 5 bridges with foundations for another 23 bridges still needing to be created
  • 42 km of temporary barriers installed along the offline section of the project (away from the current road)
  • 6km of offline haul roads have been built to allow construction traffic to move within the site without adding pressure on public roads
  • nearly 2km of utility cabling and pipes have been diverted, with another 100km still needing to be diverted
  • 13ha of archaeology work completed, revealing a roman cow, arrowheads and carving tools
  • building of the local access road between Dry Drayton and Girton has started. Once completed, people driving locally between Dry Drayton or Bar Hill and Cambridge will no longer need to use the A14
  • a new habitat for endangered water voles at Alconbury Brook is being completed, with the water voles’ planned move-in in mid-spring
  • six solar powered light towers are being trialled for night work. They don’t require generators so are green as well as quiet

Post source : Highways England