ABT SpeedyBatch more profitable than any other asphalt plant
The ABT SpeedyBatch is a perfect fit for demanding but temporary airport work, which is why business executive Jaime ArnΓ³ turned to the Ammann ABT 280 SpeedyBatch when he needed both mobility and productivity.
ArnΓ³, CEO of Benito ArnΓ³ e Hijos SA, landed a contract to provide asphalt for the reconstruction of the main runway at Spainβs Barcelona-El Prat Airport.
It was a demanding job. βFor this job, we had to manufacture 24 hours a day for almost a month,β ArnΓ³ said. βWe produced 140,000 tonnes of asphalt.βΒ The work was intense, and productivity was required. The ABT 280 SpeedyBatchβs capacity of 280 tonnes per hour was essential.
βThe work at Barcelona Airport represents an important challenge for our company,β ArnΓ³ said. βItβs a significant amount of work, which makes it difficult. There is a short execution period, as well as the fact itβs the main runway of the airport, and we couldnβt stop all the air traffic.β
As intense as the work was, the job only lasted a month. That meant the transport-optimised nature of the ABT SpeedyBatch was indispensable.
βThis plant, thanks to its modular design, let us relocate the most important elements without having to organise any special transport,β ArnΓ³ said.
The plant is transport-optimised. No special transport is needed. Cable channels are integrated into catwalks that provide protection during transport. Filler elevators and the associated costs are not necessary because reclaimed and external filler silos are part of the support structure.
Site development costs are also reduced because the plant does not require concrete foundations.
βThis plant is ideal for this type of work,β ArnΓ³ said. βIn a very short period of time, it allows us to dismantle, move it and assemble it again. We then carry out the work at a new location and repeat the dismantling process and move it to another site.β
ArnΓ³ knows the process well, as it has been repeated many times β including at other airports. βThis plant has already been transferred to other jobsites, such as Madrid-Barajas Airport, which went through practically the same runway renewal work,β he said.
ArnΓ³ is convinced only the ABT SpeedyBatch could provide the needed mobility and productivity.
βThis plant is the perfect solution,β ArnΓ³ said. βAnother solution with another type of plant carries higher assembly and dismantling costs, as well as needing more installation time. This plant, therefore, is more profitable than any other type of plant, such as semi-mobile or stationary options.β