Motorists are reminded that work to remove an 800 tonne, 250ft long bridge over the M6 in Staffordshire takes place this weekend.

The bridge, north of Stafford, will be dismantled and the entire 150-tonne centre section lifted clear and taken away in one piece on a 90ft long specialist transporter to a nearby compound.

The work forms part of plans to improve journeys in this area by adding extra capacity and technology to the motorway.

Other sections of the Creswell Home Farm bridge will be taken away later. In total, the bridge contains enough concrete to fill 40 tipper trucks. The old bridge will be recycled and used in the construction of the upgraded motorway.

While work takes place the M6, between Stafford (junction 14) and Stoke-on-Trent (junction 15), will be closed in both directions for up to 24 hours from 8pm on the evening of Saturday 22 September. It will reopen on Sunday 23 September as soon as work is completed, and it is safe to do so.

The transporter that will be used to remove the 150-tonne centre section of the bridge
The transporter that will be used to remove the 150-tonne centre section of the bridge

The bridge is no longer in use and is too narrow for the upgraded motorway which will have an extra lane in each direction.

Highways England smart motorways project sponsor, Peter Smith, said: “Demolishing the bridge is a big and complex job and to do it safely both carriageways of the motorway are needed, meaning the M6 will be closed for up to 24 hours.

“We’re doing all we can to minimise disruption. That is why we are arranging to take the centre section away in one piece, rather than breaking it up which would take more time.

“I’d like to thank motorists, businesses and residents for their patience. I’d also urge anyone wanting to use the M6 in that area to plan an alternative route to avoid congestion between Stoke and Stafford. Please also allow extra travel time and fuel for your journey.”

The transporter that will be used to remove the 150-tonne centre section of the bridge
The transporter that will be used to remove the 150-tonne centre section of the bridge

Traffic will be diverted off the M6 between junctions 14 and 15 and will use the A34 Stone Road as the diversion route. This route has been agreed with local authority partners and will be kept clear of other works during the demolition. Drivers are warned to expect delays and urged to avoid the area if possible, allowing lots of extra time for essential journeys.

To reduce M6 traffic on the day, signs will alert motorists to the closure as far away as Dover and Carlisle. Motorists and hauliers travelling between the North West and the Midlands and South of England will be urged to avoid the area by using the M62 and M1.

Work is under way with emergency services and social care providers to ensure they maintain their services along the route.

Post source : Highways England

About The Author

Anthony brings a wealth of global experience to his role as Managing Editor of Highways.Today. With an extensive career spanning several decades in the construction industry, Anthony has worked on diverse projects across continents, gaining valuable insights and expertise in highway construction, infrastructure development, and innovative engineering solutions. His international experience equips him with a unique perspective on the challenges and opportunities within the highways industry.