Construction Risk and Dispute Resolution in Focus at CCDRF 2026 Abu Dhabi
The Construction Contracts & Dispute Resolution Forum 2026 will bring more than 300 construction, development and legal professionals to Abu Dhabi on 29 and 30 September, but the agenda says as much about the pressures surrounding Gulf project delivery as it does about the event itself.
Contract strategy, risk allocation, FIDIC contracts, claims preparation, delay analysis, dispute boards, mediation and arbitration sit across the two-day programme. More than 40 speakers are expected, drawn from contractors, developers, project owners, consultants and the dispute resolution profession, with representatives from organisations including ADNOC Group, DP World, Azizi Developments and MERED.
Major Gulf projects increasingly involve long supply chains, international contractors, specialist subcontractors, multiple design interfaces and demanding delivery programmes. Managing the contract while the work is under way can therefore be as consequential as arguing about its interpretation after a disagreement has hardened into a formal dispute.
CCDRF 2026 is being organised by Great Minds Event Management in partnership with the Abu Dhabi International Arbitration Centre, arbitrateAD, and with support from the UAE Contractors Association. Its emphasis is noticeably practical: how contracts are administered, where risks are allocated, how claims develop and how disagreements can be addressed before arbitration becomes the only realistic route left.
Briefing
- CCDRF 2026 takes place at Rixos Marina Abu Dhabi on 29 and 30 September 2026.
- More than 300 senior industry professionals and over 40 speakers are expected to attend.
- The programme covers FIDIC contracts, risk allocation, claims, delay analysis, dispute boards, mediation, adjudication and arbitration.
- arbitrateAD, the Abu Dhabi International Arbitration Centre, is an event partner and provides arbitration and adjudicator appointment services.
- The programme places substantial emphasis on dispute avoidance and contract administration during project delivery rather than concentrating solely on formal proceedings after a dispute has arisen.
Managing Problems Before They Become Claims
Construction disputes rarely begin with arbitration. More often, they accumulate through instructions, variations, design changes, delayed access, extensions of time, payment disagreements, incomplete records and different interpretations of contractual responsibility.
Notices have to be issued correctly, records maintained, instructions understood and changes documented while engineers and contractors are simultaneously trying to keep the physical project moving. A disagreement that appears manageable at site level can become considerably more difficult once time has passed, personnel have moved on and the parties begin reconstructing events from correspondence, programmes and project records.
The CCDRF programme reflects that operational reality. Sessions are planned around contract strategy and risk allocation, claims preparation and delay analysis, alongside methods for preventing disagreements from progressing into formal disputes. Case studies and workshops are intended to draw directly on experience from major infrastructure and mega-project delivery.
Project directors, commercial managers, quantity surveyors, engineers and contract administrators all influence the evidence and decisions upon which a subsequent claim may depend. The forum’s expected audience reflects that overlap, with more than 100 contractors, developers and consultants anticipated alongside over 50 legal, arbitration and dispute resolution specialists.
FIDIC and Dispute Avoidance
FIDIC contracts occupy an important position in international construction and infrastructure procurement. The 2017 second edition of the FIDIC Red Book includes a Dispute Avoidance/Adjudication Agreement and procedural rules for the Dispute Avoidance/Adjudication Board, or DAAB.
FIDIC has subsequently developed practical guidance around the operation of dispute boards, including their use for dispute avoidance, appointment and the preparation of decisions. Work continuing in 2026 has also examined site visits by DAABs and how regular involvement can help identify and address disagreements while construction is still under way.
A standing dispute board develops familiarity with the contract, the project and the people delivering it. Emerging contractual disagreements can then be considered while the relevant records, personnel and site conditions remain available, rather than being reconstructed years later during formal proceedings.
CCDRF will examine dispute boards alongside mediation, adjudication and arbitration. Different mechanisms bring different costs, timescales and levels of formality, while the choice of procedure can also affect commercial relationships between organisations that may still have years of work ahead of them on the same project.
Abu Dhabi’s Arbitration Infrastructure
The forum arrives as Abu Dhabi continues to develop its institutional dispute resolution capability. The Abu Dhabi International Arbitration Centre operates as arbitrateAD, an independent organisation providing arbitration services for commercial and government entities under Arbitration Rules introduced in 2024.
The Centre also provides an adjudicator appointment service that can be written into contracts. Parties may designate arbitrateAD as the appointing authority for members of a Dispute Adjudication Board, Dispute Board or DAAB, as well as standing mediators and comparable roles. Its Court of Arbitration considers independence, expertise, experience, availability and the nature of the contract when making appointments.
This gives projects access to institutional support at different stages of a disagreement, from dispute boards operating during construction to formal arbitration when a matter cannot otherwise be resolved. The UAE is also a party to the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards, an important consideration for international businesses whose contracts, assets and counterparties may span several jurisdictions.
For those businesses, the dispute clause deserves careful attention before a contract is signed. The applicable law, seat of arbitration, language, number of arbitrators and institutional rules can become highly consequential once project-level negotiation has failed.
Contracts Across Complex Projects
Major infrastructure, transport, energy and property developments are rarely delivered through a simple chain of responsibility. A project can involve an owner, programme manager, designers, engineering consultants, principal contractors, joint ventures, specialist contractors, equipment suppliers and international supply chains, with contractual obligations extending across several organisations.
A late design decision, for example, may affect procurement, mobilisation, specialist subcontractors and the critical path. The eventual argument may concern delay or money, but understanding it requires reconstructing a sequence of decisions involving several parties and different contractual responsibilities.
Contemporary project data adds another dimension. Programmes, correspondence, BIM environments, progress records, photographs, site reports and digital approval systems can provide a much richer record of project delivery than was historically available. They can also create an enormous evidential burden when information is fragmented across different systems or has not been managed consistently.
Delay analysis illustrates the problem particularly well. Establishing that a project finished late is straightforward. Establishing which events affected the critical path, when they occurred, who was contractually responsible and what effect concurrent events had is considerably harder. The quality of contemporary project records can determine how confidently those questions can later be answered.
The CCDRF programme consequently places claims preparation and delay analysis alongside contract administration, bringing the evidence used in disputes back to the point at which much of it is actually created: during construction.
Risk Allocation Under Pressure
Contract drafting establishes where risk is intended to sit, but the practical consequences emerge during delivery. Ground conditions, access, design responsibility, inflation, variations, approvals, payment, extensions of time and changes in law can all become contentious when contractual assumptions meet conditions on site.
Standard forms such as FIDIC provide a recognised contractual architecture, but project-specific amendments remain common. Understanding those amendments, and their interaction with the underlying form, can be more important than simply knowing which standard contract appears on the cover.
CCDRF is expected to examine current FIDIC practice alongside lessons from actual projects, bringing owners, contractors and legal practitioners into the same discussions. Each approaches contractual risk from a different commercial position, and an aggressively transferred risk does not disappear simply because a contract allocates it to another party.
The consequences eventually appear somewhere in the project, whether through price, contingency, insurance, programme, claims or the willingness of contractors and suppliers to accept the work in the first place.
Keeping Construction Moving
Formal dispute resolution remains necessary. Some disagreements involve enough money, principle or complexity that arbitration or litigation cannot reasonably be avoided, and effective contracts need credible mechanisms for dealing with those cases.
More attention is nevertheless being directed towards the period before positions become entrenched. FIDIC’s work on dispute avoidance, arbitrateAD’s adjudicator appointment capability and the structure of CCDRF 2026 all place weight on mechanisms that operate while projects remain active. Their effectiveness still depends on competent contract administration, good records and a willingness to address disagreements when they emerge.
Dispute avoidance cannot remove the physical uncertainty, changing designs, commercial pressures and complicated interfaces inherent in major construction. It can bring contractual disagreements into the open while the project is active, the people involved are still available and the evidence is contemporary. For owners and contractors delivering major Gulf projects, that is a considerably better position from which to resolve a problem than reconstructing it several years later.

Key Industry Questions
- When and where is CCDRF 2026 being held? The Construction Contracts & Dispute Resolution Forum takes place on 29 and 30 September 2026 at Rixos Marina Abu Dhabi in the UAE.
- Who is expected to attend CCDRF 2026? The organisers expect more than 300 senior professionals, including project owners, contractors, developers, consultants, subcontractors, legal advisers, arbitrators and other dispute resolution specialists.
- What subjects will the forum cover? The programme includes contract strategy, risk allocation, FIDIC contracts, claims preparation, delay analysis, contract administration, dispute boards, mediation, adjudication, arbitration and regional legal developments.
- What is a DAAB under a FIDIC contract? A Dispute Avoidance/Adjudication Board is a mechanism used under FIDIC contracts to assist with dispute avoidance and to adjudicate disputes referred to it in accordance with the contract.
- Why are project records important in construction disputes? Records can establish when instructions, delays, changes and other events occurred. Programmes, correspondence, site reports and approval records may subsequently become important evidence when responsibility for time or cost is disputed.
- What is arbitrateAD? arbitrateAD is the Abu Dhabi International Arbitration Centre. It administers arbitration proceedings and also provides services including the appointment of adjudicators and dispute board members where parties have agreed to use the Centre as an appointing authority.
- Does dispute avoidance replace arbitration? No. Arbitration remains an important mechanism for resolving disputes that cannot otherwise be settled. Dispute avoidance is intended to identify and address disagreements earlier, potentially preventing some from developing into formal proceedings.
- Why does risk allocation matter in construction contracts? Contractual risk affects pricing, programme, insurance and project management. Allocating a risk contractually does not necessarily give the receiving party the practical ability to control it.
Strategic Takeaways
- Weak contract administration during construction can be difficult to repair once a disagreement has developed into a formal claim.
- Standing dispute boards can address disagreements while project personnel, records and site conditions remain readily available.
- Digital project records can strengthen the evidential basis of a claim, but fragmented or poorly managed information can create problems of its own.
- Project-specific amendments can materially alter the allocation of risk within an otherwise familiar standard form of contract.
- Abu Dhabi’s arbitration and adjudicator appointment infrastructure provides international and regional projects with several routes for managing contractual disagreements.















