Progress races forward on £68m Network Rail upgrade in East Anglia, UK
Photo Credit To Network Rail

Progress races forward on £68m Network Rail upgrade in East Anglia, UK

Progress races forward on £68m Network Rail upgrade in East Anglia, UK

Key rail works were completed last week on the Kings Lynn to Ely line and Norwich, Yarmouth, Lowestoft (Wherry lines) as part of the Network Rail wider Railway Upgrade Plan.

Team orange completed a variety of works as part of the continued modernisation of the Norwich, Yarmouth, Lowestoft lines.

NYL Piling works
NYL Piling works

Engineers worked across the area to complete the second phase of upgrades for the £68m resignalling project including remodelling of track, laying new cables, work to upgrade key level crossings and installation of 34 foundations which will eventually support the new signalling system.

At Lowestoft, 600 metres of track have been remodelled which will prepare the railway for the commissioning of the new signalling system in 2019. Enabling works have taken place at several level crossings including Lingwood and Strumpshaw with works at Cantley level crossing planned for Saturday 3 March. Six level crossings will eventually be upgraded using a modern barrier type remotely controlled by a signaller using CCTV cameras.

NYL dropping top stone down
NYL dropping top stone down

Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “The successful delivery of the second phase of the NYL project takes us one step closer to the overall goal to upgrade these lines as part of our Railway Upgrade Plan, which will transform rail travel for passengers in this region. I’d like to thank all passengers for their patience while we completed these essential works over the half term period.”

NYL Piling works
NYL Piling works

Jamie Burles, managing director, Greater Anglia, said: “This work is essential to improve reliability, and modernise and transform the railway in East Anglia. Customers were able to complete their journeys by rail replacement buses, and we would like to thank them for their patience while the work was carried out.”

Work will continue to take place on the Norwich-Yarmouth-Lowestoft lines until spring 2019 with further line closures expected in the autumn of 2018 to continue to upgrade the signalling equipment on the lines.

NYL New track panels ready for install
NYL New track panels ready for install

For more information about the project visit: www.networkrail.co.uk/nyl

Post source : Network Rail

About The Author

Anthony has worked in the construction industry for many years and looks forward to bringing you news and stories on the highways industry from all over the world.

Related posts