Doka special formwork perfect for tunnel system construction at CERN
Photo Credit To Doka GmbH

Doka special formwork perfect for tunnel system construction at CERN

Doka special formwork perfect for tunnel system construction at CERN

The Large Hadron Collider (LHC) at CERN is the biggest particle accelerator in the world – and growing: to equip the LHC for new, more ambitious experiments in the next decade, the accelerator is currently being upgraded. Doka developed three different formwork carriages and numerous special formworks to help build the tunnel system required for the upgrade.

The teams are hard at work in Meyrin (CH) and Cessy (FR). The extensive renovations will equip CERN’s particle accelerator to continue to help decode the mysteries of the universe in the coming decade. More than 500 m of tunnels and various facilities on the surface are planned for the electrical and cryogenic plants at the two sites.

Around 100,000 m³ of rock has been excavated for the new service tunnels, located a mere 10 m above the existing LHC tunnel. They are being linked to the LHC with two access points each and a number of drilled cores (for utility cables).

The smaller of the two SL-1 tunnel formwork carriages was fitted with wooden shuttering; the larger was given a steel shuttering. Copyright: Doka
The smaller of the two SL-1 tunnel formwork carriages was fitted with wooden shuttering; the larger was given a steel shuttering. Copyright: Doka

Complex workflow

The building work is being done during a planned two-year maintenance shutdown of the accelerator since vibrations during operation of the LHC could affect the experiments. The construction site team is therefore under considerable time pressure to complete the work before the planned restart of the accelerator in early 2021. The specialist in conventional and mechanical tunnel advance, Marti Tunnel AG, has built a custom steel formwork carriage for the 300 m main tunnel.

For the formwork for the cross passages, connecting components and stairwells, however, the Marti Tunnel specialists called in Doka’s expertise. The formwork engineers developing these solutions scored points partly thanks to the international cooperation between the engineering teams at Doka’s branches in Zurich and Bern and the tunnel experts in Amstetten. Various elements made the project challenging: the high complexity of the various structures, a need to ensure that formwork elements could be reused and were correctly matched with each other, and the elaborate construction workflow.

This meant it was vital for all the engineers in the project to pool their extensive expertise and knowledge and work together to ensure the client could be offered the right solution at the right time for every structure.

Only one way down: All the materials and equipment – including elements for the tunnel formwork carriages – have to be lowered by crane 60 m into the CERN access shaft. Copyright: Doka
Only one way down: All the materials and equipment – including elements for the tunnel formwork carriages – have to be lowered by crane 60 m into the CERN access shaft. Copyright: Doka

Far from traditional tunnelling

Usually, the biggest unknown at a tunnel construction site is the geology. At CERN, though, the construction site team faced rather different challenges. Natalie Schweizer explains further: “This isn’t a typical tunnel construction site. We faced a special challenge when it came to coordinating and planning each construction stage, the construction process and the materials, machines, and human resources available.” Reinforcement might be already underway in one passage while rock was being excavated 200 m away.

What made this site particularly challenging was that, although usually there is access at both sides of a tunnel, at CERN the access was constructed as a 60 m deep shaft with a diameter of 12 m. It’s not just the tunnel spoil and 17,800 m3 of in-situ concrete that have to pass through this one bottleneck – the tunnel formwork carriages are also lowered up and down through this shaft.

Doka developed the vault formwork for the four 50-70 m long cross passages, using both standard formwork methods and three formwork carriages. The largest of these SL-1 tunnel formwork carriages is 10 m long, with a diameter of 6.30 m. This carriage had to be designed so that it could be separated longitudinally, or it would not have been able to reach its destination – something that would not have been an issue on a standard tunnel construction site.

The Doka engineers accordingly planned four discs 2.5 m wide, with extra attachments that could be secured to the crane. Element by element, the 50 t gantry is lowered through the shaft into the depths. Once it reaches the bottom, excavators shunt it to its work destination with excavators, and it is assembled ready for use.

A nerve-wracking, laborious undertaking in the cramped conditions and given the limited crane capacity. The crane is assembled and positioned in the tunnel under the supervision of and with assistance from the Doka formwork instructor. Usually, formwork carriages only have to be pushed in one direction – but not so in this case. To resolve this, the Doka engineers used the bolt-on wheel sets from a Doka supporting construction frame.

With these, the four elements can be manoeuvred accurately inside the tunnel. The bolt-on wheel sets are then removed in the tunnel, and the formwork carriage is set back on its heavy-duty rollers. At the client’s request, the formwork carriage is raised and lowered hydraulically, since it would be extremely laborious to work with a manual pump in the cramped conditions.

Only one way down: All the materials and equipment – including elements for the tunnel formwork carriages – have to be lowered by crane 60 m into the CERN access shaft. Copyright: Doka
Only one way down: All the materials and equipment – including elements for the tunnel formwork carriages – have to be lowered by crane 60 m into the CERN access shaft. Copyright: Doka

About the High Luminosity LHC project – HiLumi

The Large Hadron Collider at CERN is one of the biggest and most complex scientific machines in the world. Since 2010, over 7,000 scientists from 60 countries have been working together near to the German-French border, studying the structure of matter and the fundamental interactions between elementary particles.

Various experiments and detectors have been set up along the length of the 27 km circular accelerator running beneath the Swiss canton of Geneva and part of France. The most well-known of these are ATLAS and CMS, known for their contribution to proving the existence of the Higgs boson in 2012. CERN researchers François Englert and Peter Higgs won the Nobel Prize in 2013 for this discovery.

The LHC has been extended and upgraded in the past. Now, in the course of a two-year shutdown ending in spring 2015, plus a further maintenance shutdown from 2019 until the start of 2021, the collision energy is being increased from its original 7 TeV to 13 TeV.

A kinetic energy of 7 TeV from a proton corresponds to 99.9999991% of the speed of light. One important result of the planned upgrade is that the collision rate (or, more correctly, “luminosity”) will be increased by a factor of 10, making it possible to measure new particles more precisely and observe rare interactions that it has not so far been possible to see. Supersymmetry and dark matter are just two of the universe’s mysteries that scientists hope to be able to learn more about from the LHC in the not-too-distant future

The LHC is expected to be closed down in 2035. However, various extensions and modifications are also being discussed that might be implemented before then.

Post source : Doka GmbH

About The Author

Anthony has worked in the construction industry for many years and looks forward to bringing you news and stories on the highways industry from all over the world.

Related posts