Herrenknecht TBM completes 3.2 km road tunnel in Switzerland
Photo Credit To Herrenknecht AG

Herrenknecht TBM completes 3.2 km road tunnel in Switzerland

Herrenknecht TBM completes 3.2 km road tunnel in Switzerland

The shell of the Belchen rehabilitation tunnel has been completed. Tunnelling ended successfully in Eptingen in the Swiss canton of Basel-Country on June 21, 2017, three months ahead of schedule.

The tunnel boring machine (TBM) (diameter 13.91 meters) designed and manufactured specifically for this purpose at the Herrenknecht plant in Schwanau, Germany, excavated 3.2 kilometres of tunnel through complex geology in only 16 months. The new structure is the prerequisite for rapid and economic rehabilitation of the two existing parallel road tunnel tubes.

After jobsite assembly, excavation of the 3.2 kilometer long Belchen rehabilitation tunnel began in February 2016 at the southern portal near Hägendorf (Canton of Solothurn). The tunnel alignment took the giant machine through complex geological sections with alternating rock layers.
After jobsite assembly, excavation of the 3.2 kilometer long Belchen rehabilitation tunnel began in February 2016 at the southern portal near Hägendorf (Canton of Solothurn). The tunnel alignment took the giant machine through complex geological sections with alternating rock layers.

With a diameter 13.91 meters, weight 2,000 tonnes, and a length of 75 meters, the Single Shield TBM manufactured at the Herrenknecht plant in Schwanau specifically for construction of the Belchen rehabilitation tunnel is the largest of its kind. The giant machine bored and secured up to 90 meters of tunnel per week through the complex and varied geology of the Belchen mountain range.

Under the direction of Marti Tunnelbau AG, commissioned by the Swiss Federal Roads Office FEDRO, the tunnelling crew took only 16 months for the 3.2 kilometre long drive, despite 1-shift operation Mondays to Fridays. As a result, they navigated the TBM through the mountain three months faster than originally planned.

The tunnel boring machine for the Belchen rehabilitation tunnel was handed over to the project managers of Marti Tunnelbau AG in mid-September 2015 at the Herrenknecht plant in Schwanau. With a diameter of 13.91 meters it is the largest Single Shield TBM ever built by Herrenknecht.
The tunnel boring machine for the Belchen rehabilitation tunnel was handed over to the project managers of Marti Tunnelbau AG in mid-September 2015 at the Herrenknecht plant in Schwanau. With a diameter of 13.91 meters it is the largest Single Shield TBM ever built by Herrenknecht.

After launching at the southern portal at Hägendorf (Canton of Solothurn) on February 9, 2016, the project participants celebrated the successful breakthrough at the northern portal near Eptingen (Canton of Basel-Country) on June 21, 2017. FEDRO Director Jürg Röthlisberger as well as the Baselbiet cantonal councilor Sabine Pegoraro and her Solothurn counterpart Roland Fürst among others congratulated the jobsite crew on project completion on site.

The Belchen Tunnel, which cuts through the Jura Mountains between Basel and Lucerne, is of great importance to the north-south road traffic via Gotthard as well as for domestic Swiss traffic. Currently an average of 55,000 vehicles per day over a length of almost 3.2 kilometres pass through the twin tube road tunnel of the A2 road tunnel with two lanes in each direction. As a result of increasing rock pressure, both tubes are urgently in need of repair to ensure operational safety.

The rehabilitation tunnel now completed was excavated through the mountain to the west of the two existing tubes at a distance of 40 to 116 meters from the existing tunnel system. Along the tunnel alignment the miners from Marti Tunnelbau AG mastered the challenging geological conditions with the Herrenknecht Single Shield TBM with overburdens of up to 360 meters. Soft layers of rock alternated with up to 225 MPa hard layers, in places with karstified and water-bearing transition zones. In addition, long sections of squeezing opalinus clay and swelling gypsum keuper had to be passed through.

Site manager Sergio Massignani summarized after the breakthrough: "Thanks to the comprehensive knowledge of the ground conditions from the two existing tunnel tubes, coupled with our experience and Herrenknecht's know-how, the machine was optimally designed for the demanding requirements of the alignment of the Belchen rehabilitation tunnel."
Site manager Sergio Massignani summarized after the breakthrough: “Thanks to the comprehensive knowledge of the ground conditions from the two existing tunnel tubes, coupled with our experience and Herrenknecht’s know-how, the machine was optimally designed for the demanding requirements of the alignment of the Belchen rehabilitation tunnel.”

After completion of the final works inside the tunnel and its commissioning in 2021, the two existing tubes dating from the 1970s will be renovated one after the other so that, as before, two lanes will be available in each direction, north and south, and the traffic can flow unimpeded. When the TBM was launched in February 2016, Jürg Röthlisberger summarized the concept of the project with the words “construction without queues”.

Project data

  • Project: Belchen Rehabilitation Tunnel
  • Machine type: Single Shield TBM
  • Shield diameter: 13,910 mm
  • Drive power: 3,500 kW
  • Tunnel length: 3,200 m
  • Geology: Gypsum, clay, lime, dolomites, marl
  • Customer: Marti Tunnelbau AG
  • Client: Swiss Federal Roads Office FEDRO

Post source : Herrenknecht AG

About The Author

Anthony has worked in the construction industry for many years and looks forward to bringing you news and stories on the highways industry from all over the world.

Related posts