PERI scaffold solutions prop up the Williams Bridge refurbishment in Rotterdam
Photo Credit To PERI

PERI scaffold solutions prop up the Williams Bridge refurbishment in Rotterdam

PERI scaffold solutions prop up the Williams Bridge refurbishment in Rotterdam

The refurbishment of the pylons on Rotterdam’s Williams Bridge proved to be a tremendous challenge for installing the scaffolding. The project-specifically designed PERI scaffold solution was based on two systems that could be combined with each other almost seamlessly: PERI UP and VARIOKIT.

The Williams Bridge is situated in the centre of the Dutch metropolis, Rotterdam. Besides the Erasmus Bridge and the Maas Tunnel it is one of the most important road links between the northern and southern parts of the city. The striking cable-stayed bridge over the River Maas with its two red, 60 m high steel pylons had to be renovated, therefore sandblasted and repainted. In order to ensure safe execution of the painting work, the southern pylon of the suspension bridge was scaffolded first and then the northern pylon. The pylon refurbishment was carried out on behalf of the Municipality of Rotterdam by the Venko company while Steigerbouw Van der Panne was responsible for the scaffolding work.

The projecting LGS protective roof construction on both sides ensured the safe use of the road bridge during scaffolding assembly and refurbishment work.
The projecting LGS protective roof construction on both sides ensured the safe use of the road bridge during scaffolding assembly and refurbishment work.

Challenging scaffolding operations

Installing the scaffold on the Williams Bridge was considered one of the most difficult scaffolding projects ever seen in the Netherlands. One of the requirements was that all scaffolding and painting work had to be carried out without any major negative impact on the flow of traffic in the city. As the entire superstructure is not only freely suspended through the stay cables, it was also not possible to set up the approx. 200 t scaffold construction for each respective pylon on the carriageway slab – a major challenge for all project participants.

Scaffolding the two pylons of the Williams Bridge was carried out with a PERI system combination of PERI UP and VARIOKIT.
Scaffolding the two pylons of the Williams Bridge was carried out with a PERI system combination of PERI UP and VARIOKIT.

PERI system combination

Together with the scaffolding specialists from Steigerbouw Van der Panne, PERI engineers designed an overall solution that was optimally adapted to meet project requirements, and which was based on two combinable modular systems. The PERI UP Flex Modular Scaffolding System provided flexible adaptation possibilities to match the pylon geometry and thus ensuring safe working levels including access technology. VRB Truss Girders and VST Heavy-Duty Shoring Towers taken from the VARIOKIT Engineering Construction Kit facilitated the transfer of the high loads across the entire width of the carriageway. PERI UP Flex Working Scaffold was subsequently erected on this and loads were laterally transferred via the pylon foundations. A closed, generously-sized cantilevered PERI UP intermediate level stretched over the VARIOKIT supporting structure and reliably shielded the moving traffic below as well as the pedestrian and cycle paths from the refurbishment measures and also served as a protective structure during scaffolding operations. With special drop tests using heights of more than 50 m, the protective effect was already proven in advance.

12 m wide LGS bridging served as a safe intermediate level at a height of 50 m.
12 m wide LGS bridging served as a safe intermediate level at a height of 50 m.

VARIOKIT bridging

Only one night was available for assembling the truss girders for bridging the carriageway of the structure. The girder package was therefore pre-assembled at the PERI facilities in Schijndel – each girder having a length of 21 m – and transported to the site on a heavy-duty truck. On reaching their destination, these units were quickly lifted by a mobile crane onto the VST heavy-duty towers positioned on the sides as well as on shoring and working scaffold temporarily erected in the middle of the bridge, and then coupled by means of bolts. At 6 o’clock in the morning the bridge could be re-opened. Traffic could then flow freely underneath the over 40 m high freely-supported VARIOKIT truss girder bridging.

VRB Truss Girders and VST Heavy-Duty Shoring Towers, constituent components of the VARIOKIT Engineering Construction Kit from PERI, served to transfer the high loads into the pylon foundations.
VRB Truss Girders and VST Heavy-Duty Shoring Towers, constituent components of the VARIOKIT Engineering Construction Kit from PERI, served to transfer the high loads into the pylon foundations.

LGS bridging

Parallel to the VARIOKIT heavy-duty truss girder construction for the wide-span bridging and support structure above the bridge carriageway, the LGS Lattice Girder System from the PERI UP Modular Scaffolding Kit was also used for scaffolding the pylon legs. As a result, it was possible to realize a projecting 10 m protective roof construction on both sides. In addition, a working platform with a span of 12 m could be installed between the pylon legs with the help of the LGS System. This platform moved upwards step by step in the wake of the fast scaffolding erection progress until reaching its designated final height of 50 m.

Designed to accommodate high wind loads, the scaffold anchoring and bracing was also realized with rentable VARIOKIT system components.
Designed to accommodate high wind loads, the scaffold anchoring and bracing was also realized with rentable VARIOKIT system components.

Anchoring concept

In order to hermetically seal off the working area from the road traffic as well as preventing any building and waste material from falling into the river, the PERI UP Flex Working Scaffold was completely enclosed with a shrink foil. In conjunction with the enormously high wind loads that had to be taken into consideration as a result of the Maas estuary entering the North Sea, this also required a correspondingly adapted anchoring concept. Here, too, the PERI UP Scaffolding System could be ideally combined with rentable VARIOKIT system components to form a customized and cost-effective overall solution – PERI ingenuity at its best.

40 m of carriageway bridging: overnight, the 21 m long, pre-assembled VARIOKIT Truss Girder units were lifted and coupled to VST Shoring Towers using a mobile crane. At 6 o'clock in the morning the bridge could be re-opened for traffic.
40 m of carriageway bridging: overnight, the 21 m long, pre-assembled VARIOKIT Truss Girder units were lifted and coupled to VST Shoring Towers using a mobile crane. At 6 o’clock in the morning the bridge could be re-opened for traffic.

Time-savings with high levels of safety

On the basis of the detailed joint preliminary planning along with the possibility of seamlessly integrating VARIOKIT into the PERI UP scaffolding solution, considerable time-savings were achieved in the scaffolding assembly and dismantling operations as well as in the transfer from the southern to the northern pylon. In addition, PERI UP could be erected almost tool-free resulting in fast and safe assembly: in particular, due to the self-locking ledger connection on the rosette (Gravity Lock) and the integrated lock against lifting featured on the decking (Locking Deck).

The refurbished Williams Bridge is an important road link between the northern and southern districts of Rotterdam. Its unrestricted and safe use was also to be ensured during the scaffolding operations and renovation work.
The refurbished Williams Bridge is an important road link between the northern and southern districts of Rotterdam. Its unrestricted and safe use was also to be ensured during the scaffolding operations and renovation work.

Post source : PERI

About The Author

Anthony brings a wealth of global experience to his role as Managing Editor of Highways.Today. With an extensive career spanning several decades in the construction industry, Anthony has worked on diverse projects across continents, gaining valuable insights and expertise in highway construction, infrastructure development, and innovative engineering solutions. His international experience equips him with a unique perspective on the challenges and opportunities within the highways industry.

Related posts